Whole-home remodels in Sacramento.

A whole-home remodel redesigns and rebuilds most of a house under one contract, for Sacramento-area owners who want to stay in the home with a layout that fits how they live.

14–22 weeks typical

Questions we hear a lot

Whole-home remodels FAQ.

How long does a whole-home remodel take?

Most run 14–22 weeks of construction, plus about three weeks of design and four to eight weeks of permitting before that. Plan on six to nine months from first call to moving back in.

Do we have to move out?

For whole-home work, usually yes, typically by week three or four. We help you plan the timing around it.

How are change orders handled?

On a fixed-price contract the number we quote is the number you pay unless you request a scope change; on an open-book contract you see every receipt. If you do, we price it transparently before any work starts.

Who's our point of contact during the build?

One named project manager from day one through the final walk-through, with weekly photo updates.

Do we need our own architect?

No. We design and build under one contract. Floor plans, 3D renders and finish samples take about three weeks and are done before any quote.

Is the price fixed?

It depends on size. Small and mid-size projects can get one line-itemed fixed price. Large projects are open-book cost-plus: materials and labor at cost, shown with receipts, plus a 10 to 15 percent contractor fee.

Who pulls the permits, and from which department?

We pull them. The department depends on your address: the City of Sacramento inside city limits, Sacramento County in unincorporated areas such as much of Carmichael and Fair Oaks, and Folsom, Roseville, Citrus Heights and Elk Grove each run their own. Moderate-scope permits typically take four to eight weeks.

What do you usually find behind the walls of an older Sacramento house?

Water damage and outdated plumbing or wiring are the most common finds. By era: ungrounded two-wire circuits and 60- or 100-amp services in 1950s to 1970s houses, aluminum branch wiring in houses wired between about 1965 and 1973, and corroded galvanized supply pipe before 1960. Anything we find is priced and approved by you before work proceeds.

Can a large remodel trigger seismic work?

In the City of Sacramento it can. The City amends the California Existing Building Code so that a seismic evaluation is required once work on an existing building reaches a set share of its replacement cost, 25% at our last review. On pre-1950 houses with unbraced cripple walls that can add structural scope, so we check it at design stage.

How do we know the job is finished?

When the punch list is empty. We walk the whole project with you, build the punch list together, and close every item before final payment.

Related guide: How a Sacramento renovation actually works